This document is filed with the county recorder and serves as notice to potential purchasers and lien claimants that a particular lien has been satisfied, where the party releasing the lien is a corporation and not an individual.
This document is filed with the county recorder and serves as notice to potential purchasers and lien claimants that a particular lien has been satisfied, where the party releasing the lien is a corporation and not an individual.
View Proof of Claim, Supplement 2
View Caption
View Caption (Short Title)
View Notice of Appeal and Statement of Election
View Caption for Use in Adversary Proceeding other than for a Complaint Filed by a Debtor
Request for Information from Prime Contractor - Corporation
Vermont Pre-Incorporation Agreement, Shareholders Agreement and Confidentiality Agreement
Notice to Owner - Individual
Mechanic's of Materialman's Request for Information - Individual
Lease Subordination Agreement
General Contractor's Lien - Notice of Lien - Mechanic Liens - Corporation or LLC
Lien Claim by Corporation
Bill of Sale of Automobile and Odometer Statement
Roofing Contract for Contractor
Enhanced Life Estate or Lady Bird Quitclaim Deed - Individual to Individual
When it comes to submitting Ohio Release of Mechanic's Lien - Corporation, you probably imagine a long procedure that involves choosing a suitable form among a huge selection of very similar ones and after that being forced to pay an attorney to fill it out for you. In general, that’s a slow and expensive option. Use US Legal Forms and pick out the state-specific template in a matter of clicks.
If you have a subscription, just log in and click Download to get the Ohio Release of Mechanic's Lien - Corporation form.
If you don’t have an account yet but need one, follow the step-by-step guideline listed below:
Professional lawyers work on creating our samples to ensure that after saving, you don't have to bother about editing and enhancing content outside of your individual details or your business’s info. Be a part of US Legal Forms and get your Ohio Release of Mechanic's Lien - Corporation document now.
A lien is a claim on property to ensure payment of a debt. When you borrow money to purchase a car, the lender files a lien on the vehicle with the state to insure that if the loan defaults, the lender can take the car. When the debt is fully repaid, a release of the lien is provided by the lender.
Mechanic's liens are valid for 6 years, unless a Notice to Commence Suite is served on the lien claimant. 15 A Notice to Commence Suit can be issued by the Owner or by the General Contractor, on behalf of the Owner.
While they don't require lien filings to be notarized, they do require a lien filer to jump through various other hoops that, if not done properly, might cause your filing to be rejected or invalidated: Delaware.
First, you can pay the lien off. Second, you may be able to Cancel your Contract and Eliminate the Mechanic's Lien. Third, you can file a Notice to Commence suit and Force the Contractor to act. Fourth, you can make a cash Deposit or file a bond with the court.
Mechanic's liens are valid for 6 years, unless a Notice to Commence Suite is served on the lien claimant. 15 A Notice to Commence Suit can be issued by the Owner or by the General Contractor, on behalf of the Owner.
Mechanic's liens create a cloud on title, meaning that they appear in public property records. Liens are sometimes said to travel with the land, meaning that anyone who buys your house would take the property subject to the contractor's lien (or, more likely, demand that you pay it off first).
Lien Release Bond (Ohio) An owner of property in the State of Ohio that discovers or is notified of a mechanic's lien filed against his or her property may force a resolution of the matter by filing a notice to bring suit and posting an Ohio lien release bond with the county recorder in which the property is located.
The process of bonding off a mechanics lien starts after a claimant has filed a mechanics lien. After the claim is made, a general contractor or a property owner can contact a surety bond company to purchase a surety bond that replaces the value of the lien that was filed against the property.
Note: This summary is not intended to be an all inclusive summary of the law of construction liens in Ohio, but does contain basic and other provisions.
Definitions relative to Ohio Mechanics' Liens as used in sections 1311.01 to 1311.22 of the Revised Code:
(A) "Owner," "part owner," or "lessee" includes all the
interests either legal or equitable, which such person may have in the
real estate upon which the improvements are made, including the interests
held by any person under contracts of purchase, whether in writing or otherwise.
(B) "Materialman" includes any person by whom any materials
are furnished in furtherance of an improvement.
(C) "Laborer" includes any mechanic, workman, artisan, or
other individual who performs labor or work in furtherance of any improvement.
(D) "Subcontractor" includes any person who undertakes to
construct, alter, erect, improve, repair, demolish, remove, dig, or drill
any part of any improvement under a contract with any person other than
the owner, part owner, or lessee.
(E) "Original contractor," except as otherwise provided
in section 1311.011 [1311.01.1] of the Revised Code, includes a construction
manager and any person who undertakes to construct, alter, erect, improve,
repair, demolish, remove, dig, or drill any part of any improvement under
a contract with an owner, part owner, or lessee.
(F) "Construction manager" means a person with substantial
discretion and authority to manage or direct an improvement, provided that
the person is in direct privity of contract with the owner, part owner,
or lessee of the improvement.
(G) "Notice of commencement" means the notice specified
in section 1311.04 of the Revised Code.
(H) "Notice of furnishing" means the notice specified in
section 1311.05 of the Revised Code.
(I) "Materials" means all products and substances including,
without limitation, any gasoline, lubricating oil, petroleum products,
powder, dynamite, blasting supplies and other explosives, tools, equipment,
or machinery furnished in furtherance of an improvement.
(J) "Improvement" means constructing, erecting, altering,
repairing, demolishing, or removing any building or appurtenance thereto,
fixture, bridge, or other structure, and any gas pipeline or well including,
but not limited to, a well drilled or constructed for the production of
oil or gas; the furnishing of tile for the drainage of any lot or land;
the enhancement or embellishment of real property by seeding, sodding,
or the planting thereon of any shrubs, trees, plants, vines, small fruits,
flowers, or nursery stock of any kind; and the grading or filling to establish
a grade.
(K) "Wages" means the basic hourly rate of pay and all other
contractually owed benefits.
(L) "Home construction contract" means a contract entered
into between an original contractor and an owner, part owner, or lessee
for the improvement of any single- or double family dwelling or portion
of the dwelling or a residential unit of any condominium property that
has been submitted to the provisions of Chapter 5311. of the Revised Code;
an addition to any land; or the improvement of driveways, sidewalks, swimming
pools, porches, garages, carports, landscaping, fences, fallout shelters,
siding, roofing, storm windows, awnings, and other improvements that are
adjacent to single- or double family dwellings or upon lands that are adjacent
to single- or double family dwellings or residential units of condominium
property, if the dwelling, residential unit of condominium property, or
land is used or is intended to be used as a personal residence by the owner,
part owner, or lessee.
(M) "Home purchase contract" means a contract for the purchase
of any single- or double family dwelling or residential unit of a condominium
property that has been subjected to the provisions of Chapter 5311. of
the Revised Code if the purchaser uses or intends to use the dwelling,
a unit of a double dwelling, or the condominium unit as his personal residence.
(N) "Lending institution" means any person that enters into
a contract with the owner, part owner, purchaser, or lessee to provide
financing for a home construction contract or a home purchase contract,
which financing is secured, in whole or in part, by a mortgage on the real
estate upon which the improvements contemplated by the home construction
contract are to be made or upon the property that is the subject of the
home purchase contract, and that makes direct disbursements under the contract
to any original contractor or the owner, part owner, purchaser, or lessee.
(O) "Original contractor" includes any person with whom
the owner, part owner, lessee, or purchaser under a home purchase contract
or a home construction contract has directly contracted.
Who My File a Lien?
Pursuant to Ohio statutes, a contractor, subcontractor, or materialman who has provided labor or materials to a construction project may file a lien against the property for the value of the labor performed or materials supplied by filing an Affidavit of Mechanic's Lien. A lien may not be obtained against property when the party claiming the lien has been paid in full before the property owner has received a copy of the lien claimant's Affidavit of Mechanic's Lien. O.R.C. 1311.01(B).
How Long Does a Lien Claimant Have to File a Lien?
An Affidavit for a Mechanic's Lien must be filed within sixty days from the last day of work performed by the party claiming the lien, if the project is a one or two family residential dwelling. Otherwise, the lien claimant has seventy-five (75) days to file for a lien. An exception is liens involving oil and gas leases, which may be filed within one hundred and twenty (120) days. O.R.C.1311.06(B).
What is a Notice of Commencement?
Prior to beginning work on a project which may give rise to a mechanic's lien, the property owner should file a Notice of Commencement with the county recorder in the county where the property is located. A Notice of Commencement is an affidavit which describes the improvements to be made to the property, the legal description of the property, and the names and addresses of all parties involved in the contract, along with some statutory notices, that put potential buyers or lenders on notice that improvements that may cause a lien to be filed are being made. O.R.C. 1311.04(A)(1).
A subcontractor, materialman, or laborer, may make a written request for a copy of the Notice of Commencement, to which the owner is obligated to respond within ten days. O.R.C. 1311.04(D).
What is a Notice of Furnishing?
As a counterpart to the owner's Notice of Commencement is the Notice of Furnishing that must be served by a subcontractor or materialsman on the property owner. A Notice of Furnishing serves to put the owner on notice that the party furnishing labor and materials may be entitled to a lien against the property. O.R.C. 1311.05(A)
If the Notice to Commencement has been filed, a party who wants to preserve their right to file a lien must file their Notice of Furnishing within twenty-one days of the Notice of Commencement being served. O.R.C. 1311.04(I).
How is a Lien Released?
When an Affidavit has been filed and the lien claimant has subsequently been paid, the property owner may file an affidavit attesting to the fact that the lien has been satisfied. The lienholder has thirty days from receipt of this affidavit to file a lien release or be subject to pay the property owner damages as a result. O.R.C. 1311.01(B)(3).
Lending institutions may not release funds to a contractor until that contractor has filed an affidavit stating that the contractor has paid all subcontractors, laborers, and materialmen in full, and that there are no further claims pending against the project. A property owner may issue written demand that the contractor issue this affidavit and may withhold payment until the affidavit is received. O.R.C. 1311.01(B)(4).
If there is a dispute between subcontractors and the principal contractor regarding payment, such that the subcontractor will not release his lien, under Ohio statutes, the property owner is entitled to withhold payment to the principal contractor in the amount of the lien. In response, the principal contractor and lending institution may demand that the lien holder provide them with information regarding the amount of the lien and the dates upon which work was performed. The owner or lending institution may only release payment to the original contractor when the lien holder has given notice that he has been paid, the subcontractor issues a lien release, the original contractor provides a bond, or the time under which a lien may be filed has expired. O.R.C. 1311.01(B)(8).
How Else May a Property Owner Respond to a Lien?
After a lien has been filed, a property owner may serve a Notice to the Lien holder to Commence Suit. Within thirty days of serving the notice the property owner must file the notice with an affidavit indicating how service was accomplished. The lien holder has sixty days after being served to file suit or his lien will be rendered void. O.R.C. 1311.11(B)(3)
Note: This summary is not intended to be an all inclusive summary of the law of construction liens in Ohio, but does contain basic and other provisions.
Definitions relative to Ohio Mechanics' Liens as used in sections 1311.01 to 1311.22 of the Revised Code:
(A) "Owner," "part owner," or "lessee" includes all the
interests either legal or equitable, which such person may have in the
real estate upon which the improvements are made, including the interests
held by any person under contracts of purchase, whether in writing or otherwise.
(B) "Materialman" includes any person by whom any materials
are furnished in furtherance of an improvement.
(C) "Laborer" includes any mechanic, workman, artisan, or
other individual who performs labor or work in furtherance of any improvement.
(D) "Subcontractor" includes any person who undertakes to
construct, alter, erect, improve, repair, demolish, remove, dig, or drill
any part of any improvement under a contract with any person other than
the owner, part owner, or lessee.
(E) "Original contractor," except as otherwise provided
in section 1311.011 [1311.01.1] of the Revised Code, includes a construction
manager and any person who undertakes to construct, alter, erect, improve,
repair, demolish, remove, dig, or drill any part of any improvement under
a contract with an owner, part owner, or lessee.
(F) "Construction manager" means a person with substantial
discretion and authority to manage or direct an improvement, provided that
the person is in direct privity of contract with the owner, part owner,
or lessee of the improvement.
(G) "Notice of commencement" means the notice specified
in section 1311.04 of the Revised Code.
(H) "Notice of furnishing" means the notice specified in
section 1311.05 of the Revised Code.
(I) "Materials" means all products and substances including,
without limitation, any gasoline, lubricating oil, petroleum products,
powder, dynamite, blasting supplies and other explosives, tools, equipment,
or machinery furnished in furtherance of an improvement.
(J) "Improvement" means constructing, erecting, altering,
repairing, demolishing, or removing any building or appurtenance thereto,
fixture, bridge, or other structure, and any gas pipeline or well including,
but not limited to, a well drilled or constructed for the production of
oil or gas; the furnishing of tile for the drainage of any lot or land;
the enhancement or embellishment of real property by seeding, sodding,
or the planting thereon of any shrubs, trees, plants, vines, small fruits,
flowers, or nursery stock of any kind; and the grading or filling to establish
a grade.
(K) "Wages" means the basic hourly rate of pay and all other
contractually owed benefits.
(L) "Home construction contract" means a contract entered
into between an original contractor and an owner, part owner, or lessee
for the improvement of any single- or double family dwelling or portion
of the dwelling or a residential unit of any condominium property that
has been submitted to the provisions of Chapter 5311. of the Revised Code;
an addition to any land; or the improvement of driveways, sidewalks, swimming
pools, porches, garages, carports, landscaping, fences, fallout shelters,
siding, roofing, storm windows, awnings, and other improvements that are
adjacent to single- or double family dwellings or upon lands that are adjacent
to single- or double family dwellings or residential units of condominium
property, if the dwelling, residential unit of condominium property, or
land is used or is intended to be used as a personal residence by the owner,
part owner, or lessee.
(M) "Home purchase contract" means a contract for the purchase
of any single- or double family dwelling or residential unit of a condominium
property that has been subjected to the provisions of Chapter 5311. of
the Revised Code if the purchaser uses or intends to use the dwelling,
a unit of a double dwelling, or the condominium unit as his personal residence.
(N) "Lending institution" means any person that enters into
a contract with the owner, part owner, purchaser, or lessee to provide
financing for a home construction contract or a home purchase contract,
which financing is secured, in whole or in part, by a mortgage on the real
estate upon which the improvements contemplated by the home construction
contract are to be made or upon the property that is the subject of the
home purchase contract, and that makes direct disbursements under the contract
to any original contractor or the owner, part owner, purchaser, or lessee.
(O) "Original contractor" includes any person with whom
the owner, part owner, lessee, or purchaser under a home purchase contract
or a home construction contract has directly contracted.
Who My File a Lien?
Pursuant to Ohio statutes, a contractor, subcontractor, or materialman who has provided labor or materials to a construction project may file a lien against the property for the value of the labor performed or materials supplied by filing an Affidavit of Mechanic's Lien. A lien may not be obtained against property when the party claiming the lien has been paid in full before the property owner has received a copy of the lien claimant's Affidavit of Mechanic's Lien. O.R.C. 1311.01(B).
How Long Does a Lien Claimant Have to File a Lien?
An Affidavit for a Mechanic's Lien must be filed within sixty days from the last day of work performed by the party claiming the lien, if the project is a one or two family residential dwelling. Otherwise, the lien claimant has seventy-five (75) days to file for a lien. An exception is liens involving oil and gas leases, which may be filed within one hundred and twenty (120) days. O.R.C.1311.06(B).
What is a Notice of Commencement?
Prior to beginning work on a project which may give rise to a mechanic's lien, the property owner should file a Notice of Commencement with the county recorder in the county where the property is located. A Notice of Commencement is an affidavit which describes the improvements to be made to the property, the legal description of the property, and the names and addresses of all parties involved in the contract, along with some statutory notices, that put potential buyers or lenders on notice that improvements that may cause a lien to be filed are being made. O.R.C. 1311.04(A)(1).
A subcontractor, materialman, or laborer, may make a written request for a copy of the Notice of Commencement, to which the owner is obligated to respond within ten days. O.R.C. 1311.04(D).
What is a Notice of Furnishing?
As a counterpart to the owner's Notice of Commencement is the Notice of Furnishing that must be served by a subcontractor or materialsman on the property owner. A Notice of Furnishing serves to put the owner on notice that the party furnishing labor and materials may be entitled to a lien against the property. O.R.C. 1311.05(A)
If the Notice to Commencement has been filed, a party who wants to preserve their right to file a lien must file their Notice of Furnishing within twenty-one days of the Notice of Commencement being served. O.R.C. 1311.04(I).
How is a Lien Released?
When an Affidavit has been filed and the lien claimant has subsequently been paid, the property owner may file an affidavit attesting to the fact that the lien has been satisfied. The lienholder has thirty days from receipt of this affidavit to file a lien release or be subject to pay the property owner damages as a result. O.R.C. 1311.01(B)(3).
Lending institutions may not release funds to a contractor until that contractor has filed an affidavit stating that the contractor has paid all subcontractors, laborers, and materialmen in full, and that there are no further claims pending against the project. A property owner may issue written demand that the contractor issue this affidavit and may withhold payment until the affidavit is received. O.R.C. 1311.01(B)(4).
If there is a dispute between subcontractors and the principal contractor regarding payment, such that the subcontractor will not release his lien, under Ohio statutes, the property owner is entitled to withhold payment to the principal contractor in the amount of the lien. In response, the principal contractor and lending institution may demand that the lien holder provide them with information regarding the amount of the lien and the dates upon which work was performed. The owner or lending institution may only release payment to the original contractor when the lien holder has given notice that he has been paid, the subcontractor issues a lien release, the original contractor provides a bond, or the time under which a lien may be filed has expired. O.R.C. 1311.01(B)(8).
How Else May a Property Owner Respond to a Lien?
After a lien has been filed, a property owner may serve a Notice to the Lien holder to Commence Suit. Within thirty days of serving the notice the property owner must file the notice with an affidavit indicating how service was accomplished. The lien holder has sixty days after being served to file suit or his lien will be rendered void. O.R.C. 1311.11(B)(3)